Pakistan · regulator determination · unnumbered (NEPRA approval of ISMO wheeling auction framework)
Competitive electricity wheeling auction mechanism (Framework Guidelines for Wheeling Auctions)
Competitive electricity wheeling auction mechanism (Framework Guidelines for Wheeling Auctions)
Summary
NEPRA approved an auction framework submitted by ISMO that allocates up to 800 MW of demand for wheeling under the CTBCM, with a minimum load of 1 MW per participant and a cap of 20% (160 MW) for any bidder or affiliated group. It builds on Framework Guidelines for Wheeling Auctions issued on 2026-01-22.
Reviewer notes: Scouted from desk research (low confidence). From Profit (Pakistan Today), 2026-03-25 (secondary); approval date and NEPRA decision number not found. The article also cites amendments to the National Electricity Plan and supplier licensing rules notified in August 2025 (not recorded). NEPRA's site lists an ISMO wheeling auction notice (July 2026).
History
No amendment or revocation links are recorded for this rule yet.
Implementation
This rule implements CTBCM commercial operations.
Related rules in Pakistan
Change log
-
Added to the tracker.
Cite this entry
Wheeling auction mechanism 2026, “Competitive electricity wheeling auction mechanism (Framework Guidelines for Wheeling Auctions)”. National Electric Power Regulatory Authority (NEPRA); Independent System and Market Operator (ISMO), Pakistan, signed Mar 2026. In: Power Transformation Lab Policy Tracker, status checked 19 Nov 2026. https://power-lab.github.io/policy-tracker/rules/pk-dec-2026-wheelauction/