Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects
Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects
Summary
Guidelines under section 63 of the Electricity Act for procurers buying power from grid-connected solar PV projects through tariff-based competitive bidding. They set the bidding process, contract terms and the allocation of risks between procurers and generators, and replace the 2017 solar bidding guidelines for new tenders.
Reviewer notes: Scouted from desk research (medium confidence). Dates (27 July 2023, effective 28 July 2023) from secondary copies; the MNRE document page returned 404. MNRE lists a later version dated 2024-02-02 (status set to amended). The 2017 guidelines (2017-08-03) are not recorded. Check the resolution number and the 2024 changes.
History
No amendment or revocation links are recorded for this rule yet.
Implementation
This rule implements Electricity Act 2003.
Related rules in India
Change log
-
Added to the tracker.
Cite this entry
Solar TBCB guidelines 2023, “Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects”. Ministry of Power, India, signed 27 Jul 2023. In: Power Transformation Lab Policy Tracker, status checked 19 Nov 2026. https://power-lab.github.io/policy-tracker/rules/in-res-mop-2023-solar-tbcb/