India · decision · unnumbered (Ministry of Power order dated 2021-11-23; file number not confirmed)

Waiver of inter-state transmission (ISTS) charges for electricity from solar and wind sources

Waiver of Inter-State Transmission Charges on transmission of the electricity generated from solar and wind sources of energy

in force unverified

Summary

Ministry of Power order waiving inter-state transmission charges for solar and wind projects commissioned by 30 June 2025, with the waiver reduced by 25% a year for projects commissioned after that date. The waiver now operates through the CERC Sharing of Inter-State Transmission Charges and Losses Regulations, 2020, as amended (fourth amendment dated 2025-06-26).

Not yet verified. This entry has not been fully checked against the official text. Confirm the status and links before relying on it.

Reviewer notes: Scouted from desk research (medium confidence). Date of the base order (23 November 2021) is cited in later Ministry of Power amendments; the order PDF at powermin.gov.in returned 404 after the site migration. The waiver schedule (100% to 2025-06-30, then 25% annual reduction, 25 years from commissioning) is from the Rajya Sabha answer of 2026-03-17 (PIB 2241170). Separate orders cover hydro (late 2022), storage, green hydrogen and offshore wind; extensions for grid-delayed projects were issued in 2023-2024. Check the current status of the waiver and whether the order is now superseded by the CERC regulations.

History

No amendment or revocation links are recorded for this rule yet.

Implementation

This rule implements Electricity Act 2003.

Related rules in India

Change log

  1. Added to the tracker.

Cite this entry

ISTS charge waiver order 2021, “Waiver of inter-state transmission (ISTS) charges for electricity from solar and wind sources”. Ministry of Power, India, signed 23 Nov 2021. In: Power Transformation Lab Policy Tracker, status checked 19 Nov 2026. https://power-lab.github.io/policy-tracker/rules/in-order-mop-2021-ists/