Thailand · decision · 1/2567 (167)

NEPC resolution on measures allowing private parties to sign direct power purchase agreements (Direct PPA)

NEPC resolution on measures allowing private parties to sign direct power purchase agreements (Direct PPA)

amended unverified

Summary

Starts a Direct PPA pilot that allows data centres to buy renewable power directly from generators over the grid through third-party access, up to 2,000 MW. The NEPC widened it to industry generally and removed the cap in July 2026.

Not yet verified. This entry has not been fully checked against the official text. Confirm the status and links before relying on it.

Reviewer notes: Scouted from desk research (high confidence). Thai title to be added. The ERC published a draft Direct PPA Regulation and draft TPA Code on 3 Oct 2025 (eligibility: BOI-promoted data centre with at least 50 MW IT load; new renewable plant of at least 1,000 kVA without an existing PPA); final issue not confirmed, so no row yet. date_in_force taken as the meeting date.

History

All instruments linked to this one by amendment, revocation or partial override, in order of signature. Select an instrument to open its entry.

2024202520262027NEPC 2024-06 Direct PPA: amended, signed 25 Jun 2024NEPC 2024-06 Direct PPANEPC 2026-07 Direct PPA: in force, signed 15 Jul 2026NEPC 2026-07 Direct PPA

revokes or replaces amends overrides in part in force amended pending draft replaced revoked expired

  1. NEPC 2024-06 Direct PPA (this rule) 25 Jun 2024 amended
    NEPC resolution on measures allowing private parties to sign direct power purchase agreements (Direct PPA)
  2. NEPC 2026-07 Direct PPA 15 Jul 2026 in force
    NEPC resolution on criteria for the pilot Direct PPA for renewable power through third-party access (TPA)

Related rules in Thailand

Change log

  1. Added to the tracker.

Cite this entry

NEPC 2024-06 Direct PPA, “NEPC resolution on measures allowing private parties to sign direct power purchase agreements (Direct PPA)”. National Energy Policy Council (NEPC), Thailand, signed 25 Jun 2024. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/th-nepc-2024-1-direct-ppa/