Thailand · decision · 2/2569 (176)
NEPC resolution on criteria for the pilot Direct PPA for renewable power through third-party access (TPA)
NEPC resolution on criteria for the pilot Direct PPA for renewable power through third-party access (TPA)
Summary
Opens the Direct PPA pilot beyond data centres to industry generally and removes the 2,000 MW cap. EPAC selects and supervises participants, and data centres pay security deposits for grid use.
Reviewer notes: Scouted from desk research (high confidence). Thai title to be added. EPAC approved principles on 3 Aug 2026; the ERC then consulted. Final ERC Direct PPA regulation and TPA Code not confirmed as issued (one unverified post claims Gazette publication on 14 Aug 2026). Link basis not checked against the text: the report says it amends or replaces the earlier row. date_in_force taken as the meeting date.
History
All instruments linked to this one by amendment, revocation or partial override, in order of signature. Select an instrument to open its entry.
revokes or replaces amends overrides in part in force amended pending draft replaced revoked expired
-
NEPC resolution on measures allowing private parties to sign direct power purchase agreements (Direct PPA)
-
NEPC 2026-07 Direct PPA (this rule) 15 Jul 2026 in forceNEPC resolution on criteria for the pilot Direct PPA for renewable power through third-party access (TPA)Amends NEPC 2024-06 Direct PPA.
Related rules in Thailand
Change log
-
Added to the tracker.
Cite this entry
NEPC 2026-07 Direct PPA, “NEPC resolution on criteria for the pilot Direct PPA for renewable power through third-party access (TPA)”. National Energy Policy Council (NEPC), Thailand, signed 15 Jul 2026. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/th-nepc-2026-2-direct-ppa-tpa/