Malaysia · regulator determination · GP/ST/No.40/2024

Guidelines for Corporate Renewable Energy Supply Scheme (CRESS)

Guidelines for Corporate Renewable Energy Supply Scheme (CRESS)

amended unverified

Summary

Sets up third-party access in Peninsular Malaysia: a renewable energy developer can supply a green consumer over TNB's network and pays the Single Buyer a system access charge. The charge was 25 sen/kWh for firm and 45 sen/kWh for non-firm supply at launch, and PETRA reduced it to 20 and 40 sen for RP4 on 29 August 2025. 51% local ownership is a licence condition.

Not yet verified. This entry has not been fully checked against the official text. Confirm the status and links before relying on it.

Reviewer notes: Scouted from desk research (high confidence). Registered guideline under s.50C of Act 447. First version effective 20 Sep 2024 (Skrine); no separate signing date recorded, so date_signed repeats it. Revised twice (rows -REV1, -REV2). The 29 Aug 2025 SAC cut was a PETRA press release (PETRA.100-9/1/4 JLD.1 (39); not a row); check whether a revision codified it. See also MY-DEC-2026-CAP.

History

All instruments linked to this one by amendment, revocation or partial override, in order of signature. Select an instrument to open its entry.

202420252026CRESS Guidelines: amended, signed 20 Sep 2024CRESS GuidelinesCRESS Guidelines Mar 2025: in force, signed 1 Mar 2025CRESS Guidelines Mar 2025CRESS Guidelines Pindaan 2025: in force, signed 26 Dec 2025CRESS Guidelines Pindaan 2025

revokes or replaces amends overrides in part in force amended pending draft replaced revoked expired

  1. CRESS Guidelines (this rule) 20 Sep 2024 amended
    Guidelines for Corporate Renewable Energy Supply Scheme (CRESS)
  2. CRESS Guidelines Mar 2025 1 Mar 2025 in force
    Guidelines for Corporate Renewable Energy Supply Scheme (CRESS), second version (March 2025)
  3. CRESS Guidelines Pindaan 2025 26 Dec 2025 in force
    Guidelines for Corporate Renewable Energy Supply Scheme (CRESS), third version (December 2025)

Implementation

This rule implements Act 447.

Related rules in Malaysia

Change log

  1. Added to the tracker.

Cite this entry

CRESS Guidelines, “Guidelines for Corporate Renewable Energy Supply Scheme (CRESS)”. Energy Commission (Suruhanjaya Tenaga), Malaysia, signed 20 Sep 2024. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/my-gp-2024-40/