Thailand · decision · 1/2568 (171)
NEPC resolution on the remaining additional renewable procurement under the 2023-2030 clean power plan
NEPC resolution on the remaining additional renewable procurement under the 2023-2030 clean power plan
Summary
Resumes the 3,668.5 MW additional procurement round after the December 2024 deferral. It directs the ERC, EGAT, PEA, MEA and EPPO to start negotiations with the selected applicants.
Reviewer notes: Scouted from desk research (medium confidence). Thai title to be added. Follow-up resolutions on 21 Aug and 27 Oct 2025 (EPPO portal) not yet rows. Link basis not checked against the text: the report says it amends or replaces the earlier row. date_in_force taken as the meeting date.
History
All instruments linked to this one by amendment, revocation or partial override, in order of signature. Select an instrument to open its entry.
revokes or replaces amends overrides in part in force amended pending draft replaced revoked expired
-
NEPC resolution on additional renewable procurement (no-fuel-cost group and industrial waste) under FiT 2022-2030
-
NEPC 2025-05 FiT resumed (this rule) 6 May 2025 in forceNEPC resolution on the remaining additional renewable procurement under the 2023-2030 clean power planAmends NEPC 2023-03 additional FiT.
Related rules in Thailand
Change log
-
Added to the tracker.
Cite this entry
NEPC 2025-05 FiT resumed, “NEPC resolution on the remaining additional renewable procurement under the 2023-2030 clean power plan”. National Energy Policy Council (NEPC), Thailand, signed 6 May 2025. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/th-nepc-2025-1-fit-additional/