Malaysia · decision · unnumbered (procurement round)
Notice of issue of the Request for Proposal for the sixth Large Scale Solar competitive bidding round (LSS6)
Notis Makluman Pengapungan Dokumen Request For Proposal Bagi Program Bidaan Terbuka Large Scale Solar
Summary
Opens the sixth Large Scale Solar bidding round in Peninsular Malaysia for 2,650 MW of solar and 1,250 MW/6,000 MWh of battery storage. It is split into three packages: an open solar-plus-storage package (2,200 MW plus 1,100 MW of storage), a Bumiputera solar-plus-storage package (300 MW plus 150 MW of storage) and a Bumiputera solar-only package (150 MW).
Reviewer notes: Scouted from desk research (high confidence). Notice dated 24 Jul 2026 (Malay). No document number found; the title is taken from the file name, so check it against the notice. RFP sales 27 Jul-7 Aug 2026 (hybrid) and 17-28 Aug 2026 (solar only). COD target 31 Dec 2029 is per the press. Earlier rounds LSS4 (2020), LSS5 (RFP Apr 2024) and LSS PETRA 5+ (Jan 2025) are not rows.
History
No amendment or revocation links are recorded for this rule yet.
Related rules in Malaysia
Change log
-
Added to the tracker.
Cite this entry
LSS6 RFP, “Notice of issue of the Request for Proposal for the sixth Large Scale Solar competitive bidding round (LSS6)”. Ministry of Energy Transition and Water Transformation (PETRA), through the Energy Commission (Suruhanjaya Tenaga), Malaysia, signed 24 Jul 2026. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/my-dec-2026-lss6/