Malaysia · regulator determination · GP/ST/No.51/2024
Guidelines for Solar Photovoltaic Installation for Self-Consumption (SELCO) in Peninsular Malaysia
Guidelines for Solar Photovoltaic Installation for Self-Consumption in Peninsular Malaysia
Summary
Sets the rules for solar installations for self-consumption in Peninsular Malaysia, without credit for exported power. It replaced the 2017 guidelines on connecting self-consumption solar (GP/ST/No.13/2017). Under an Energy Commission notice of 31 December 2025, the standby charge of RM12/kWp and the battery storage requirement apply only above 1 MWac; the battery rule used to apply above 72 kWp.
Reviewer notes: Scouted from desk research (high confidence). Registered guideline under s.50C of Act 447; in operation 1 Jan 2025; registration date known only to the year. Revised twice (rows -REV1, -REV2). GP/ST/No.13/2017 (Pin.2023), which it revokes, is not a row. The 31 Dec 2025 ST notice (Notis Makluman, https://www.st.gov.my/sites/default/files/2026-03/Notis-Makluman-31.12.2025.pdf) is not a row; the standby charge threshold was previously 1 MWp. A separate SELCO guideline covers Kulim Hi-Tech Park (2025).
History
All instruments linked to this one by amendment, revocation or partial override, in order of signature. Select an instrument to open its entry.
revokes or replaces amends overrides in part in force amended pending draft replaced revoked expired
-
SELCO Guidelines (this rule) 2024 amendedGuidelines for Solar Photovoltaic Installation for Self-Consumption (SELCO) in Peninsular Malaysia
-
Guidelines for Solar Photovoltaic Installation for Self-Consumption in Peninsular Malaysia, 2025 revisionAmends SELCO Guidelines.
-
Guidelines for Solar Photovoltaic Installation for Self-Consumption in Peninsular Malaysia, 2026 revisionAmends SELCO Guidelines.
Implementation
This rule implements Act 447.
Related rules in Malaysia
Change log
-
Added to the tracker.
Cite this entry
SELCO Guidelines, “Guidelines for Solar Photovoltaic Installation for Self-Consumption (SELCO) in Peninsular Malaysia”. Energy Commission (Suruhanjaya Tenaga), Malaysia, signed 2024. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/my-gp-2024-51/