The NEM 3.0 programme for 2021-2025: homes (NEM Rakyat) and government premises (NEM GoMEn, up to 1,000 kW) in Peninsular Malaysia offset exported solar power one-for-one against their consumption for 10 years, within a total of up to 2,500 MW. New applications ended on 30 June 2025, but the guidelines still govern existing participants.
Reviewer notes: Scouted from desk research (high confidence). Registered guideline under s.50C of Act 447; first version 29 Jan 2021, effective date not recorded. NEM 3.0 was announced by KeTSA on 29 Dec 2020. The 2,500 MW total and the 30 Jun 2025 closing date are per SEDA. Eight versions in all (rows -REV1 to -REV7). The PDF at the URL is the current text (Pin.1/2026).
History
All instruments linked to this one by amendment, revocation or partial override, in order of signature. Select an instrument to open its entry.
revokes or replaces amends overrides in part in force amended pending draft replaced revoked expired
-
NEM Rakyat & GoMEn Guidelines (this rule) 29 Jan 2021 amendedGuidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia
-
Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia, revision of 15 July 2023Amends NEM Rakyat & GoMEn Guidelines.
-
Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia, revision of 5 February 2024Amends NEM Rakyat & GoMEn Guidelines.
-
Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia, revision of 1 April 2024Amends NEM Rakyat & GoMEn Guidelines.
-
Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia, revision of 20 September 2024Amends NEM Rakyat & GoMEn Guidelines.
-
Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia, revision of 25 November 2024Amends NEM Rakyat & GoMEn Guidelines.
-
Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia, revision of 1 March 2025Amends NEM Rakyat & GoMEn Guidelines.
-
Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia, 2026 revisionAmends NEM Rakyat & GoMEn Guidelines.
Implementation
This rule implements Act 447.
Related rules in Malaysia
Change log
-
Added to the tracker.
Cite this entry
NEM Rakyat & GoMEn Guidelines, “Guidelines for Solar Photovoltaic Installation under the Programme of NEM Rakyat and NEM GoMEn in Peninsular Malaysia”. Energy Commission (Suruhanjaya Tenaga), Malaysia, signed 29 Jan 2021. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/my-gp-2021-27/