Malaysia · regulator determination · GP/ST/No.1/2016

Guidelines on Large Scale Solar Photovoltaic Plant for Connection to Electricity Networks

Guidelines on Large Scale Solar Photovoltaic Plant for Connection to Electricity Networks

amended unverified

Summary

Sets the development framework and grid-connection rules for plants in the Large Scale Solar auction rounds, including injection points, milestones to commercial operation and licensing.

Not yet verified. This entry has not been fully checked against the official text. Confirm the status and links before relying on it.

Reviewer notes: Scouted from desk research (high confidence). Registered guideline under s.50C of Act 447; registered 28 Apr 2016, effective date not recorded. Pre-2017, kept because the LSS rounds still run under it. Revised three times (rows -REV1 to -REV3). The SEDA LSS page still links a dead 2019 copy under /contents/2019/LSS/.

History

All instruments linked to this one by amendment, revocation or partial override, in order of signature. Select an instrument to open its entry.

20162018202020222024LSS Connection Guidelines: amended, signed 28 Apr 2016LSS Connection GuidelinesLSS Connection Guidelines Pin.2019: in force, signed 20 Dec 2018LSS Connection Guidelines Pin.2019LSS Connection Guidelines Pin.2020: in force, signed 20 May 2020LSS Connection Guidelines Pin.2020LSS Connection Guidelines Pin.2024: in force, signed 2 Apr 2024LSS Connection Guidelines Pin.2024

revokes or replaces amends overrides in part in force amended pending draft replaced revoked expired

  1. LSS Connection Guidelines (this rule) 28 Apr 2016 amended
    Guidelines on Large Scale Solar Photovoltaic Plant for Connection to Electricity Networks
  2. LSS Connection Guidelines Pin.2019 20 Dec 2018 in force
    Guidelines on Large Scale Solar Photovoltaic Plant for Connection to Electricity Networks, revision of 20 December 2018
  3. LSS Connection Guidelines Pin.2020 20 May 2020 in force
    Guidelines on Large Scale Solar Photovoltaic Plant for Connection to Electricity Networks, revision of 20 May 2020
  4. Guidelines on Large Scale Solar Photovoltaic Plant for Connection to Electricity Networks, revision of 2 April 2024

Implementation

This rule implements Act 447.

Related rules in Malaysia

Change log

  1. Added to the tracker.

Cite this entry

LSS Connection Guidelines, “Guidelines on Large Scale Solar Photovoltaic Plant for Connection to Electricity Networks”. Energy Commission (Suruhanjaya Tenaga), Malaysia, signed 28 Apr 2016. In: Power Transformation Lab Policy Tracker, status checked 4 Nov 2026. https://power-lab.github.io/policy-tracker/rules/my-gp-2016-1/